Meridian High School
Bauder Total Roof System PLUS with Bauder structural rooflights
Synopsis
Meridian High School is a coeducational secondary school with academy status, located in the New Addington area of the London Borough of Croydon.
Meridian High School. Credit: Skyler Contracting Ltd
Meridian High School. Credit: Skyler Contracting Ltd
Meridian High School. Credit: Skyler Contracting Ltd
Meridian High School. Credit: Skyler Contracting Ltd
Meridian High School. Credit: Skyler Contracting Ltd
Bauder Building Board
Project: |
Meridian High School |
Location: |
Croydon |
Project type: |
Refurbishment |
Roof size: |
2046m² |
Specifier: |
Daniel Connal Partnership |
Building owner: |
GLF Schools |
Approved contractor: |
Skyler Contracting Limited |
The specification
Bauder area technical manager, Chris Clarke, carried out a condition report on the flat roof areas that were causing concern. Core samples were taken from various locations of the roof. They identified that areas of the deck were damp, confirming that the waterproofing was failing there. A visual appraisal showed that several of the roof areas had substantial greenery growing on them and detritus that was, in some instances, blocking the guttering. The roof surface was showing typical signs of ageing such as surface oxidisation, cracks, splits, blisters, rucks, and laps coming apart.
The thermal performance of the existing roof build-up was poor and well below current standards. One of the risks associated with inadequate levels of insulation is the potential for condensation to form within the structure or waterproofing system during periods of climatic extreme. The insulation on this project would need to be upgraded to meet current Building Regulation requirements.
The survey confirmed that the existing waterproofing on much of the building had come to the end of its service life and needed refurbishment before a serious failure occurred. The proposal for renovation included upgrading the insulation, replacing the rooflights and increasing the upstand height around the glazing.
Products applied
Bauder Total Roof System PLUS
Fully integrated bituminous roof system, featuring the most advanced
bitumen membrane currently available, BauderKARAT.
BauderPIR FA-TE
PIR insulation in a variety of thicknesses to achieve the required U-value for the school. Ideal where weight loadings may be a consideration.
Structural rooflights
Modern thermally efficient structural rooflight, and kerbs were raised where necessary to create a minimum upstand of 150mm.
System installed
Bauder Total Roof System PLUS
1 BauderKARAT cap sheet |
5.2mm thick dual modified APP/SBS, torch applied bitumen cap sheet offering the ultimate waterproofing solution. |
2 BauderTEC KSA DUO 35 Underlayer |
A self-adhesive elastomeric bitumen underlayer. |
3 PIR FA-TE insulation |
BauderPIR FA-TE Insulation was used on this project to upgrade the thermal performance of the building to meet current standards. Various thicknesses were used on the different roof areas. |
4 VB4-EXPAL |
This robust bitumen AVCL provides temporary waterproofing once laid, ideal for refurbishing a dilapidated roof. |